Timeline for FirstEnergy Ohio Utilities’ February 2021 PIPP RFP |
Delivery Period: June 1, 2021 to May 31, 2022 |
Activity | Date |
Pre-Procurement Activity |
|
Bidder Information Session | Thursday, January 14, 2021 |
PIPP Supplier Application can be submitted | Thursday, January 14, 2021 |
Announcement of blended SSO price (tentative) | Wednesday, January 27, 2021 |
PIPP Supplier Application is due | Friday, January 29, 2021 |
Notifications to Registered Bidders | Tuesday, February 2, 2021 |
February 8, 2021 RFP |
|
Pre-bid security due | Thursday, February 4, 2021 |
Bid window to submit bids (10:00 AM to 02:00 PM ET) | Monday, February 8, 2021 |
CRA notifies the Companies and PUCO of results (tentative) | Monday, February 8, 2021 |
PUCO acceptance of results (tentative) | Wednesday, February 10, 2021 |
Master PIPP Supply Agreement signed (tentative) | Friday, February 12, 2021 |
Power flow | Tuesday, June 1, 2021 |
2021 Supplemental RFP (if necessary) |
|
Pre-bid security due | Thursday, February 18, 2021 |
Bid window to submit bids (10:00 AM to 02:00 PM ET) | Monday, February 22, 2021 |
CRA notifies the Companies and PUCO of results (tentative) | Monday, February 22, 2021 |
PUCO acceptance of results (tentative) | Wednesday, February 24, 2021 |
Master PIPP Supply Agreement signed (tentative) | Friday, February 26, 2021 |
Power flow | Tuesday, June 1, 2021 |