Timeline for FirstEnergy Ohio Utilities’ March 2026 PIPP RFP
Delivery Period: June 1, 2026 to May 31, 2027
Activity Date
Pre-Procurement Activity  
Bidder Information Session Wednesday, February 18, 2026
Announcement of blended SSO price  Wednesday, February 18, 2026
PIPP Supplier Application can be submitted Thursday, February 19, 2026
PIPP Supplier Application is due Wednesday, March 4, 2026
Notifications to Registered Bidders Monday, March 9, 2026
March 16, 2026 RFP  
Pre-bid security due Wednesday, March 11, 2026
Bid window to submit bids (10:00 AM to 02:00 PM ET) Monday, March 16, 2026
CRA notifies the Companies and PUCO of results (tentative) Monday, March 16, 2026
PUCO acceptance of results (tentative) Wednesday, March 18, 2026
Master PIPP Supply Agreement signed (tentative) Friday, March 20, 2026
Power Flow Monday, June 1, 2026
2026 Supplemental RFP (if necessary)  
Pre-bid security due Wednesday, March 25, 2026
Bid window to submit bids (10:00 AM to 02:00 PM ET) Monday, March 30, 2026
CRA notifies the Companies and PUCO of results (tentative) Monday, March 30, 2026
PUCO acceptance of results (tentative) Wednesday, April 1, 2026
Master PIPP Supply Agreement signed (tentative) Friday, April 3, 2026
Power Flow Monday, June 1, 2026
 